{"id":13294,"date":"2021-04-06T14:05:41","date_gmt":"2021-04-06T14:05:41","guid":{"rendered":"https:\/\/arvengtraining.com\/?p=13294"},"modified":"2022-01-14T12:12:39","modified_gmt":"2022-01-14T11:12:39","slug":"changes-in-piping-during-the-construction-phase","status":"publish","type":"post","link":"https:\/\/arvengtraining.com\/en\/changes-in-piping-during-the-construction-phase\/","title":{"rendered":"Changes in piping during the construction phase"},"content":{"rendered":"<p>When a change is identified during construction, a lot of effort is put into identifying the impact of the change for cost, schedule, engineering\/design and materials, and then having the change order approved.<\/p>\n<p><strong>Change is always disruptive during construction.\u00a0 The crew has to stop what they are working on, make the existing area safe, and then be moved to another area.\u00a0 Subsequent crews scheduled to be in the area may need to be diverted to other work.<\/strong>\u00a0 The work schedule will need to be reassessed.\u00a0 Equipment, tools and materials for the new area have to be arranged.\u00a0 Getting back into the original area to complete the disrupted work depends on the delivery of engineering drawings, revised materials, and available manpower.<\/p>\n<p>As noted in a previous blog, in many engineering companies, each individual discipline is usually challenged to work within the lowest possible budget \u2013 both for workhours and for material costs.\u00a0 Unless the designers are astute, there can be some unintended consequences.<\/p>\n<p><strong>Although a change can impact many disciplines, this post will only deal briefly with steel and pipe.\u00a0 <\/strong>Materials for changes need to be selected and sourced with the schedule (as well as the cost) in mind.\u00a0 Steel structures should be easy to fabricate in the shop, and\/or assemble on site.\u00a0 It may be worth discussing with the steel fabricator what sections are available, or are easy to obtain.\u00a0 If the change involves an unusual size of type of pipe, it is worth discussing with the materials management department to see if there is anything currently available that could be diverted to the change, or if they could make a few calls to see if any of their suppliers have any (properly documented) spare materials.\u00a0 Any materials that are diverted will likely need to be reordered, so the time and cost for this needs to be taken into account.<\/p>\n<p><strong>Once the steel and\/or pipe has been fabricated, it needs to be delivered to the site.\u00a0 It can be worth discussing with transportation whether the additional cost of an LTL (less than truck load) or a hot shot is warranted<\/strong>.\u00a0 If either is warranted, there will already be an existing system in place to notify the site that the material is coming.\u00a0 If neither is warranted, and the site is not advised that the materials are coming, it may take additional time for the materials to be directed to the correct area.<\/p>\n<p>The true cost of the change can be difficult to ascertain, particularly for duration related indirect costs.\u00a0 It is difficult to tell if the cumulative effect of several smaller changes (however meticulously documented) or some other situation causes the project to finish later than scheduled.\u00a0 It is usually a combination of events, and ascertaining the proportion of the time and costs to be applied to each of the events can be very challenging.\u00a0 The impact of a change can increase the later it is identified.<\/p>\n<p><strong>Experienced engineers\/designers understand the importance of understanding all aspects of a change, and take the overall impact to the job into account when they make recommendations on how to deal with a change.<\/strong><\/p>\n<p align=\"left\">If you want to know more:<\/p>\n<p align=\"left\"><a href=\"https:\/\/arvengtraining.com\/en\/all-courses\/asme-viii-design-pressure-vessels-online\/\">ASME VIII | Design of Pressure Vessels<\/a><\/p>\n<p align=\"left\"><a href=\"https:\/\/arvengtraining.com\/en\/all-courses\/tema-design-of-shell-and-tube-heat-exchangers-online\/\">TEMA | Design of Shell &amp; Tube Heat Exchangers<\/a><\/p>\n<p align=\"left\"><a href=\"https:\/\/arvengtraining.com\/en\/all-courses\/asme-b31-piping-systems-for-industrial-plants-online\/\">ASME B31 | Piping Systems for Industrial Plants<\/a><\/p>\n","protected":false},"excerpt":{"rendered":"<p>When a change is identified during construction, a lot of effort is put into identifying the impact of the change for cost, schedule, engineering\/design and materials, and then having the change order approved. Change is always disruptive during construction.\u00a0 The crew has to stop what they are working on, make the existing area safe, and [&hellip;]<\/p>\n","protected":false},"author":483,"featured_media":13292,"comment_status":"closed","ping_status":"open","sticky":false,"template":"","format":"standard","meta":{"footnotes":""},"categories":[323],"tags":[804,911,912,913,914],"class_list":["post-13294","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-piping-en","tag-construction","tag-change-order","tag-cost","tag-planning","tag-piping-systems"],"yoast_head":"<!-- This site is optimized with the Yoast SEO plugin v27.3 - https:\/\/yoast.com\/product\/yoast-seo-wordpress\/ -->\n<title>Changes in piping during the construction phase - Arveng Training &amp; Engineering<\/title>\n<meta name=\"robots\" content=\"index, follow, max-snippet:-1, max-image-preview:large, max-video-preview:-1\" \/>\n<link rel=\"canonical\" href=\"https:\/\/arvengtraining.com\/en\/changes-in-piping-during-the-construction-phase\/\" \/>\n<meta property=\"og:locale\" content=\"en_US\" \/>\n<meta property=\"og:type\" content=\"article\" \/>\n<meta property=\"og:title\" content=\"Changes in piping during the construction phase - Arveng Training &amp; Engineering\" \/>\n<meta property=\"og:description\" content=\"When a change is identified during construction, a lot of effort is put into identifying the impact of the change for cost, schedule, engineering\/design and materials, and then having the change order approved. Change is always disruptive during construction.\u00a0 The crew has to stop what they are working on, make the existing area safe, and [&hellip;]\" \/>\n<meta property=\"og:url\" content=\"https:\/\/arvengtraining.com\/en\/changes-in-piping-during-the-construction-phase\/\" \/>\n<meta property=\"og:site_name\" content=\"Arveng Training &amp; Engineering\" \/>\n<meta property=\"article:publisher\" content=\"https:\/\/www.facebook.com\/ArvengTraining\" \/>\n<meta property=\"article:published_time\" content=\"2021-04-06T14:05:41+00:00\" \/>\n<meta property=\"article:modified_time\" content=\"2022-01-14T11:12:39+00:00\" \/>\n<meta property=\"og:image\" content=\"https:\/\/arvengtraining.com\/wp-content\/uploads\/2021\/04\/1.-Changes-during-construction-Bonnie-Baker.jpg\" \/>\n\t<meta property=\"og:image:width\" content=\"1200\" \/>\n\t<meta property=\"og:image:height\" content=\"675\" \/>\n\t<meta property=\"og:image:type\" content=\"image\/jpeg\" \/>\n<meta name=\"author\" content=\"Bonnie Baker\" \/>\n<meta name=\"twitter:card\" content=\"summary_large_image\" \/>\n<meta name=\"twitter:image\" content=\"https:\/\/arvengtraining.com\/wp-content\/uploads\/2021\/04\/1.-Changes-during-construction-Bonnie-Baker.jpg\" \/>\n<meta name=\"twitter:creator\" content=\"@ArvengTraining\" \/>\n<meta name=\"twitter:site\" content=\"@ArvengTraining\" \/>\n<meta name=\"twitter:label1\" content=\"Written by\" \/>\n\t<meta name=\"twitter:data1\" content=\"Bonnie Baker\" \/>\n\t<meta name=\"twitter:label2\" content=\"Est. reading time\" \/>\n\t<meta name=\"twitter:data2\" content=\"3 minutes\" \/>\n<script type=\"application\/ld+json\" class=\"yoast-schema-graph\">{\"@context\":\"https:\\\/\\\/schema.org\",\"@graph\":[{\"@type\":\"Article\",\"@id\":\"https:\\\/\\\/arvengtraining.com\\\/en\\\/changes-in-piping-during-the-construction-phase\\\/#article\",\"isPartOf\":{\"@id\":\"https:\\\/\\\/arvengtraining.com\\\/en\\\/changes-in-piping-during-the-construction-phase\\\/\"},\"author\":{\"name\":\"Bonnie Baker\",\"@id\":\"https:\\\/\\\/arvengtraining.com\\\/#\\\/schema\\\/person\\\/6553edf8437483d1b0895bf6a9c5fc9e\"},\"headline\":\"Changes in piping during the construction phase\",\"datePublished\":\"2021-04-06T14:05:41+00:00\",\"dateModified\":\"2022-01-14T11:12:39+00:00\",\"mainEntityOfPage\":{\"@id\":\"https:\\\/\\\/arvengtraining.com\\\/en\\\/changes-in-piping-during-the-construction-phase\\\/\"},\"wordCount\":557,\"publisher\":{\"@id\":\"https:\\\/\\\/arvengtraining.com\\\/#organization\"},\"image\":{\"@id\":\"https:\\\/\\\/arvengtraining.com\\\/en\\\/changes-in-piping-during-the-construction-phase\\\/#primaryimage\"},\"thumbnailUrl\":\"https:\\\/\\\/arvengtraining.com\\\/wp-content\\\/uploads\\\/2021\\\/04\\\/1.-Changes-during-construction-Bonnie-Baker.jpg\",\"keywords\":[\"Construction\",\"Change order\",\"cost\",\"planning\",\"Piping Systems\"],\"articleSection\":[\"Piping\"],\"inLanguage\":\"en-US\"},{\"@type\":\"WebPage\",\"@id\":\"https:\\\/\\\/arvengtraining.com\\\/en\\\/changes-in-piping-during-the-construction-phase\\\/\",\"url\":\"https:\\\/\\\/arvengtraining.com\\\/en\\\/changes-in-piping-during-the-construction-phase\\\/\",\"name\":\"Changes in piping during the construction phase - Arveng Training &amp; Engineering\",\"isPartOf\":{\"@id\":\"https:\\\/\\\/arvengtraining.com\\\/#website\"},\"primaryImageOfPage\":{\"@id\":\"https:\\\/\\\/arvengtraining.com\\\/en\\\/changes-in-piping-during-the-construction-phase\\\/#primaryimage\"},\"image\":{\"@id\":\"https:\\\/\\\/arvengtraining.com\\\/en\\\/changes-in-piping-during-the-construction-phase\\\/#primaryimage\"},\"thumbnailUrl\":\"https:\\\/\\\/arvengtraining.com\\\/wp-content\\\/uploads\\\/2021\\\/04\\\/1.-Changes-during-construction-Bonnie-Baker.jpg\",\"datePublished\":\"2021-04-06T14:05:41+00:00\",\"dateModified\":\"2022-01-14T11:12:39+00:00\",\"breadcrumb\":{\"@id\":\"https:\\\/\\\/arvengtraining.com\\\/en\\\/changes-in-piping-during-the-construction-phase\\\/#breadcrumb\"},\"inLanguage\":\"en-US\",\"potentialAction\":[{\"@type\":\"ReadAction\",\"target\":[\"https:\\\/\\\/arvengtraining.com\\\/en\\\/changes-in-piping-during-the-construction-phase\\\/\"]}]},{\"@type\":\"ImageObject\",\"inLanguage\":\"en-US\",\"@id\":\"https:\\\/\\\/arvengtraining.com\\\/en\\\/changes-in-piping-during-the-construction-phase\\\/#primaryimage\",\"url\":\"https:\\\/\\\/arvengtraining.com\\\/wp-content\\\/uploads\\\/2021\\\/04\\\/1.-Changes-during-construction-Bonnie-Baker.jpg\",\"contentUrl\":\"https:\\\/\\\/arvengtraining.com\\\/wp-content\\\/uploads\\\/2021\\\/04\\\/1.-Changes-during-construction-Bonnie-Baker.jpg\",\"width\":1200,\"height\":675},{\"@type\":\"BreadcrumbList\",\"@id\":\"https:\\\/\\\/arvengtraining.com\\\/en\\\/changes-in-piping-during-the-construction-phase\\\/#breadcrumb\",\"itemListElement\":[{\"@type\":\"ListItem\",\"position\":1,\"name\":\"Portada\",\"item\":\"https:\\\/\\\/arvengtraining.com\\\/en\\\/\"},{\"@type\":\"ListItem\",\"position\":2,\"name\":\"Changes in piping during the construction phase\"}]},{\"@type\":\"WebSite\",\"@id\":\"https:\\\/\\\/arvengtraining.com\\\/#website\",\"url\":\"https:\\\/\\\/arvengtraining.com\\\/\",\"name\":\"Arveng Training Engineering | Cursos y Master en Ingenier\u00eda\",\"description\":\"We provide Specialized Training &amp; Engineering Services, answers and solutions for specific requirements.\",\"publisher\":{\"@id\":\"https:\\\/\\\/arvengtraining.com\\\/#organization\"},\"alternateName\":\"Arveng Training & Engineering - Formaci\u00f3n en ingenier\u00eda online\\\/presencial\",\"potentialAction\":[{\"@type\":\"SearchAction\",\"target\":{\"@type\":\"EntryPoint\",\"urlTemplate\":\"https:\\\/\\\/arvengtraining.com\\\/?s={search_term_string}\"},\"query-input\":{\"@type\":\"PropertyValueSpecification\",\"valueRequired\":true,\"valueName\":\"search_term_string\"}}],\"inLanguage\":\"en-US\"},{\"@type\":[\"Organization\",\"Place\"],\"@id\":\"https:\\\/\\\/arvengtraining.com\\\/#organization\",\"name\":\"Arveng Training Engineering | Cursos y Master en Ingenier\u00eda\",\"url\":\"https:\\\/\\\/arvengtraining.com\\\/\",\"logo\":{\"@id\":\"https:\\\/\\\/arvengtraining.com\\\/en\\\/changes-in-piping-during-the-construction-phase\\\/#local-main-organization-logo\"},\"image\":{\"@id\":\"https:\\\/\\\/arvengtraining.com\\\/en\\\/changes-in-piping-during-the-construction-phase\\\/#local-main-organization-logo\"},\"sameAs\":[\"https:\\\/\\\/www.facebook.com\\\/ArvengTraining\",\"https:\\\/\\\/x.com\\\/ArvengTraining\",\"https:\\\/\\\/www.linkedin.com\\\/in\\\/arvengtraining\\\/\",\"http:\\\/\\\/wwwyoutube.com\\\/ArvengTraining\",\"https:\\\/\\\/www.instagram.com\\\/arveng_training\",\"https:\\\/\\\/www.linkedin.com\\\/company\\\/arvengtraining\\\/\"],\"address\":{\"@id\":\"https:\\\/\\\/arvengtraining.com\\\/en\\\/changes-in-piping-during-the-construction-phase\\\/#local-main-place-address\"},\"geo\":{\"@type\":\"GeoCoordinates\",\"latitude\":\"40.488398\",\"longitude\":\"-3.67123715\"},\"telephone\":[\"913 40 88 51\"],\"contactPoint\":{\"@type\":\"ContactPoint\",\"telephone\":\"913408851\",\"email\":\"info@arvenggroup.com\"},\"openingHoursSpecification\":[{\"@type\":\"OpeningHoursSpecification\",\"dayOfWeek\":[\"Monday\",\"Tuesday\",\"Wednesday\",\"Thursday\",\"Friday\"],\"opens\":\"09:00\",\"closes\":\"17:30\"},{\"@type\":\"OpeningHoursSpecification\",\"dayOfWeek\":[\"Saturday\",\"Sunday\"],\"opens\":\"00:00\",\"closes\":\"00:00\"}],\"email\":\"info@arvenggroup.com\",\"vatID\":\"B87794293\"},{\"@type\":\"Person\",\"@id\":\"https:\\\/\\\/arvengtraining.com\\\/#\\\/schema\\\/person\\\/6553edf8437483d1b0895bf6a9c5fc9e\",\"name\":\"Bonnie Baker\",\"image\":{\"@type\":\"ImageObject\",\"inLanguage\":\"en-US\",\"@id\":\"https:\\\/\\\/secure.gravatar.com\\\/avatar\\\/fa1c4e784f8bf77413f52c5ec3dc6cfb280eda6f60c0960157744b7ed1a20ed2?s=96&d=mm&r=g\",\"url\":\"https:\\\/\\\/secure.gravatar.com\\\/avatar\\\/fa1c4e784f8bf77413f52c5ec3dc6cfb280eda6f60c0960157744b7ed1a20ed2?s=96&d=mm&r=g\",\"contentUrl\":\"https:\\\/\\\/secure.gravatar.com\\\/avatar\\\/fa1c4e784f8bf77413f52c5ec3dc6cfb280eda6f60c0960157744b7ed1a20ed2?s=96&d=mm&r=g\",\"caption\":\"Bonnie Baker\"}},{\"@type\":\"PostalAddress\",\"@id\":\"https:\\\/\\\/arvengtraining.com\\\/en\\\/changes-in-piping-during-the-construction-phase\\\/#local-main-place-address\",\"streetAddress\":\"Av. de Manoteras, 10, edificio b oficina 111, Hortaleza\",\"addressLocality\":\"Madrid\",\"postalCode\":\"28050\",\"addressRegion\":\"Madrid\",\"addressCountry\":\"ES\"},{\"@type\":\"ImageObject\",\"inLanguage\":\"en-US\",\"@id\":\"https:\\\/\\\/arvengtraining.com\\\/en\\\/changes-in-piping-during-the-construction-phase\\\/#local-main-organization-logo\",\"url\":\"https:\\\/\\\/arvengtraining.com\\\/wp-content\\\/uploads\\\/2020\\\/04\\\/ARVENG-RGB-LOGO-VECTORIAL-2-840x430-1-e1588673301938.jpg\",\"contentUrl\":\"https:\\\/\\\/arvengtraining.com\\\/wp-content\\\/uploads\\\/2020\\\/04\\\/ARVENG-RGB-LOGO-VECTORIAL-2-840x430-1-e1588673301938.jpg\",\"width\":750,\"height\":384,\"caption\":\"Arveng Training Engineering | Cursos y Master en Ingenier\u00eda\"}]}<\/script>\n<meta name=\"geo.placename\" content=\"Madrid\" \/>\n<meta name=\"geo.position\" content=\"40.488398;-3.67123715\" \/>\n<meta name=\"geo.region\" content=\"Spain\" \/>\n<!-- \/ Yoast SEO plugin. -->","yoast_head_json":{"title":"Changes in piping during the construction phase - Arveng Training &amp; Engineering","robots":{"index":"index","follow":"follow","max-snippet":"max-snippet:-1","max-image-preview":"max-image-preview:large","max-video-preview":"max-video-preview:-1"},"canonical":"https:\/\/arvengtraining.com\/en\/changes-in-piping-during-the-construction-phase\/","og_locale":"en_US","og_type":"article","og_title":"Changes in piping during the construction phase - Arveng Training &amp; Engineering","og_description":"When a change is identified during construction, a lot of effort is put into identifying the impact of the change for cost, schedule, engineering\/design and materials, and then having the change order approved. Change is always disruptive during construction.\u00a0 The crew has to stop what they are working on, make the existing area safe, and [&hellip;]","og_url":"https:\/\/arvengtraining.com\/en\/changes-in-piping-during-the-construction-phase\/","og_site_name":"Arveng Training &amp; Engineering","article_publisher":"https:\/\/www.facebook.com\/ArvengTraining","article_published_time":"2021-04-06T14:05:41+00:00","article_modified_time":"2022-01-14T11:12:39+00:00","og_image":[{"width":1200,"height":675,"url":"https:\/\/arvengtraining.com\/wp-content\/uploads\/2021\/04\/1.-Changes-during-construction-Bonnie-Baker.jpg","type":"image\/jpeg"}],"author":"Bonnie Baker","twitter_card":"summary_large_image","twitter_image":"https:\/\/arvengtraining.com\/wp-content\/uploads\/2021\/04\/1.-Changes-during-construction-Bonnie-Baker.jpg","twitter_creator":"@ArvengTraining","twitter_site":"@ArvengTraining","twitter_misc":{"Written by":"Bonnie Baker","Est. reading time":"3 minutes"},"schema":{"@context":"https:\/\/schema.org","@graph":[{"@type":"Article","@id":"https:\/\/arvengtraining.com\/en\/changes-in-piping-during-the-construction-phase\/#article","isPartOf":{"@id":"https:\/\/arvengtraining.com\/en\/changes-in-piping-during-the-construction-phase\/"},"author":{"name":"Bonnie Baker","@id":"https:\/\/arvengtraining.com\/#\/schema\/person\/6553edf8437483d1b0895bf6a9c5fc9e"},"headline":"Changes in piping during the construction phase","datePublished":"2021-04-06T14:05:41+00:00","dateModified":"2022-01-14T11:12:39+00:00","mainEntityOfPage":{"@id":"https:\/\/arvengtraining.com\/en\/changes-in-piping-during-the-construction-phase\/"},"wordCount":557,"publisher":{"@id":"https:\/\/arvengtraining.com\/#organization"},"image":{"@id":"https:\/\/arvengtraining.com\/en\/changes-in-piping-during-the-construction-phase\/#primaryimage"},"thumbnailUrl":"https:\/\/arvengtraining.com\/wp-content\/uploads\/2021\/04\/1.-Changes-during-construction-Bonnie-Baker.jpg","keywords":["Construction","Change order","cost","planning","Piping Systems"],"articleSection":["Piping"],"inLanguage":"en-US"},{"@type":"WebPage","@id":"https:\/\/arvengtraining.com\/en\/changes-in-piping-during-the-construction-phase\/","url":"https:\/\/arvengtraining.com\/en\/changes-in-piping-during-the-construction-phase\/","name":"Changes in piping during the construction phase - Arveng Training &amp; Engineering","isPartOf":{"@id":"https:\/\/arvengtraining.com\/#website"},"primaryImageOfPage":{"@id":"https:\/\/arvengtraining.com\/en\/changes-in-piping-during-the-construction-phase\/#primaryimage"},"image":{"@id":"https:\/\/arvengtraining.com\/en\/changes-in-piping-during-the-construction-phase\/#primaryimage"},"thumbnailUrl":"https:\/\/arvengtraining.com\/wp-content\/uploads\/2021\/04\/1.-Changes-during-construction-Bonnie-Baker.jpg","datePublished":"2021-04-06T14:05:41+00:00","dateModified":"2022-01-14T11:12:39+00:00","breadcrumb":{"@id":"https:\/\/arvengtraining.com\/en\/changes-in-piping-during-the-construction-phase\/#breadcrumb"},"inLanguage":"en-US","potentialAction":[{"@type":"ReadAction","target":["https:\/\/arvengtraining.com\/en\/changes-in-piping-during-the-construction-phase\/"]}]},{"@type":"ImageObject","inLanguage":"en-US","@id":"https:\/\/arvengtraining.com\/en\/changes-in-piping-during-the-construction-phase\/#primaryimage","url":"https:\/\/arvengtraining.com\/wp-content\/uploads\/2021\/04\/1.-Changes-during-construction-Bonnie-Baker.jpg","contentUrl":"https:\/\/arvengtraining.com\/wp-content\/uploads\/2021\/04\/1.-Changes-during-construction-Bonnie-Baker.jpg","width":1200,"height":675},{"@type":"BreadcrumbList","@id":"https:\/\/arvengtraining.com\/en\/changes-in-piping-during-the-construction-phase\/#breadcrumb","itemListElement":[{"@type":"ListItem","position":1,"name":"Portada","item":"https:\/\/arvengtraining.com\/en\/"},{"@type":"ListItem","position":2,"name":"Changes in piping during the construction phase"}]},{"@type":"WebSite","@id":"https:\/\/arvengtraining.com\/#website","url":"https:\/\/arvengtraining.com\/","name":"Arveng Training Engineering | Cursos y Master en Ingenier\u00eda","description":"We provide Specialized Training &amp; Engineering Services, answers and solutions for specific requirements.","publisher":{"@id":"https:\/\/arvengtraining.com\/#organization"},"alternateName":"Arveng Training & Engineering - Formaci\u00f3n en ingenier\u00eda online\/presencial","potentialAction":[{"@type":"SearchAction","target":{"@type":"EntryPoint","urlTemplate":"https:\/\/arvengtraining.com\/?s={search_term_string}"},"query-input":{"@type":"PropertyValueSpecification","valueRequired":true,"valueName":"search_term_string"}}],"inLanguage":"en-US"},{"@type":["Organization","Place"],"@id":"https:\/\/arvengtraining.com\/#organization","name":"Arveng Training Engineering | Cursos y Master en Ingenier\u00eda","url":"https:\/\/arvengtraining.com\/","logo":{"@id":"https:\/\/arvengtraining.com\/en\/changes-in-piping-during-the-construction-phase\/#local-main-organization-logo"},"image":{"@id":"https:\/\/arvengtraining.com\/en\/changes-in-piping-during-the-construction-phase\/#local-main-organization-logo"},"sameAs":["https:\/\/www.facebook.com\/ArvengTraining","https:\/\/x.com\/ArvengTraining","https:\/\/www.linkedin.com\/in\/arvengtraining\/","http:\/\/wwwyoutube.com\/ArvengTraining","https:\/\/www.instagram.com\/arveng_training","https:\/\/www.linkedin.com\/company\/arvengtraining\/"],"address":{"@id":"https:\/\/arvengtraining.com\/en\/changes-in-piping-during-the-construction-phase\/#local-main-place-address"},"geo":{"@type":"GeoCoordinates","latitude":"40.488398","longitude":"-3.67123715"},"telephone":["913 40 88 51"],"contactPoint":{"@type":"ContactPoint","telephone":"913408851","email":"info@arvenggroup.com"},"openingHoursSpecification":[{"@type":"OpeningHoursSpecification","dayOfWeek":["Monday","Tuesday","Wednesday","Thursday","Friday"],"opens":"09:00","closes":"17:30"},{"@type":"OpeningHoursSpecification","dayOfWeek":["Saturday","Sunday"],"opens":"00:00","closes":"00:00"}],"email":"info@arvenggroup.com","vatID":"B87794293"},{"@type":"Person","@id":"https:\/\/arvengtraining.com\/#\/schema\/person\/6553edf8437483d1b0895bf6a9c5fc9e","name":"Bonnie Baker","image":{"@type":"ImageObject","inLanguage":"en-US","@id":"https:\/\/secure.gravatar.com\/avatar\/fa1c4e784f8bf77413f52c5ec3dc6cfb280eda6f60c0960157744b7ed1a20ed2?s=96&d=mm&r=g","url":"https:\/\/secure.gravatar.com\/avatar\/fa1c4e784f8bf77413f52c5ec3dc6cfb280eda6f60c0960157744b7ed1a20ed2?s=96&d=mm&r=g","contentUrl":"https:\/\/secure.gravatar.com\/avatar\/fa1c4e784f8bf77413f52c5ec3dc6cfb280eda6f60c0960157744b7ed1a20ed2?s=96&d=mm&r=g","caption":"Bonnie Baker"}},{"@type":"PostalAddress","@id":"https:\/\/arvengtraining.com\/en\/changes-in-piping-during-the-construction-phase\/#local-main-place-address","streetAddress":"Av. de Manoteras, 10, edificio b oficina 111, Hortaleza","addressLocality":"Madrid","postalCode":"28050","addressRegion":"Madrid","addressCountry":"ES"},{"@type":"ImageObject","inLanguage":"en-US","@id":"https:\/\/arvengtraining.com\/en\/changes-in-piping-during-the-construction-phase\/#local-main-organization-logo","url":"https:\/\/arvengtraining.com\/wp-content\/uploads\/2020\/04\/ARVENG-RGB-LOGO-VECTORIAL-2-840x430-1-e1588673301938.jpg","contentUrl":"https:\/\/arvengtraining.com\/wp-content\/uploads\/2020\/04\/ARVENG-RGB-LOGO-VECTORIAL-2-840x430-1-e1588673301938.jpg","width":750,"height":384,"caption":"Arveng Training Engineering | Cursos y Master en Ingenier\u00eda"}]},"geo.placename":"Madrid","geo.position":{"lat":"40.488398","long":"-3.67123715"},"geo.region":"Spain"},"_links":{"self":[{"href":"https:\/\/arvengtraining.com\/en\/wp-json\/wp\/v2\/posts\/13294","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/arvengtraining.com\/en\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/arvengtraining.com\/en\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/arvengtraining.com\/en\/wp-json\/wp\/v2\/users\/483"}],"replies":[{"embeddable":true,"href":"https:\/\/arvengtraining.com\/en\/wp-json\/wp\/v2\/comments?post=13294"}],"version-history":[{"count":0,"href":"https:\/\/arvengtraining.com\/en\/wp-json\/wp\/v2\/posts\/13294\/revisions"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/arvengtraining.com\/en\/wp-json\/wp\/v2\/media\/13292"}],"wp:attachment":[{"href":"https:\/\/arvengtraining.com\/en\/wp-json\/wp\/v2\/media?parent=13294"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/arvengtraining.com\/en\/wp-json\/wp\/v2\/categories?post=13294"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/arvengtraining.com\/en\/wp-json\/wp\/v2\/tags?post=13294"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}